November 2026 · #30DayMapChallenge 2026 · Day 20

Day 20 - Hexagons: Where the Sun Is Not

Greece in 7 km hexagons: the sun each one gets, and the solar parks asked for in it. Since 2000, 117.6 GW of solar has been asked of the regulator, and 58% of it has since been withdrawn, rejected or lapsed. What is left crowds into Macedonia and Thessaly, while the sunniest quarter of the land holds 6% of it. Play the years to watch the rush.

Printed map
Printed A4 sheet titled Where the Sun Is Not: Greece drawn as small hexagons tinted from pale yellow in the northern mountains to deep orange and red on Crete, the Cyclades and the Dodecanese, with black hexagons inside them, largest in Thessaly, western Macedonia and around Kozani, and thin outlines for the parks asked for; notes mark two 7 GW claims and Crete, with the most sun and almost no parks; Kastellorizo in an inset; the side panel holds a legend, a bar chart of the solar parks asked for by year, a chart of land and parks by sun class and three figures

Click a hexagon for its numbers. Zoom in to see the parks themselves.

Move the slider, or press play, to see the register grow year by year: the outline is everything asked for by then, the solid hexagon what is still alive today. Click a hexagon for its sun and its parks; zoom in to see the parks themselves.

Downloads

Prompt: Hexagons.

Greece gets more sun than almost anywhere in Europe, and it has been building solar parks fast. But the parks are not where the sun is strongest. This map cuts the country into hexagons of 7 km a side, 1,662 of them, and shows two things in each: how much sun it gets, and how much solar power has been asked for in it.

The sun

The tint is the yearly output of 1 kWp of solar panels at the best tilt, from the EU’s PVGIS model (SARAH-3 satellite data, 2005-2023), averaged over the land in each hexagon. It runs from about 1,150 kWh in the Pindus mountains to over 1,700 kWh on the south coast of Crete and in the Dodecanese, and the islands of the south Aegean as a whole get the most.

The parks

The parks come from the register of the energy regulator, RAAEY: 4,877 solar parks with their outlines, power and licence stage. Each park’s power is shared among the hexagons it covers, by area. Inside each hexagon, a dark hexagon is the power still alive (licensed, under review or sent to the grid operator), and an outline is everything ever asked for. Both grow with the area, and a hexagon is full at 1 GW.

Power Share
Asked for since 2000 117.6 GW 100%
Withdrawn, rejected or lapsed 68.1 GW 58%
Still alive 49.6 GW 42%

Almost all of it came in one rush: 88% of the power in the register was asked for between 2019 and 2024. The slider on the web map shows it arriving.

Not where the sun is

Apart from the two claims below, what is alive crowds into the plains of Thessaly and Macedonia, and around Kozani and Ptolemaida, where solar parks are being built on the old lignite mines. These are places with flat, open land and with the big power lines and substations that once served the lignite plants. The sunniest quarter of the land, at 1,500 kWh/kWp and more, holds only 6% of the power still alive. Crete has the most sun and almost no parks.

Sun, kWh per kWp Share of the land Share of the power alive
under 1,300 4.6% 0.8%
1,300 to 1,400 28.3% 14.1%
1,400 to 1,500 41.7% 79.1%
1,500 to 1,600 19.1% 5.7%
1,600 to 1,700 5.9% 0.2%
1,700 and more 0.4% 0.0%

Two 7 GW claims

Two applications from 2024 stand out. Two energy communities each ask for 7,000 MW, one in Boeotia and Evia, one at Boukka on the Amvrakikos Gulf. Both are still under review, so they count as alive: together 14 of the 49.6 GW. The map labels them. Both had applied in 2023 as well, for 7 GW at Boukka and 11.65 GW in Boeotia, Evia and Phthiotis, and withdrawn those applications.

What the register does not show

  • Small parks and rooftops. The register lists parks that need RAAEY’s licence. Rooftop systems and most small parks never pass through it, and in Greece they are a large part of what is built.
  • What is built. Only 3 GW in the register carries an operating licence, but more than that runs today: many built parks keep the stage they had when they were licensed. So “alive” here means not withdrawn, not built.
  • The grid. The pattern points to the grid, but the map does not draw it. How much room each substation has left is not published in a form that can be mapped.

How it was made

The register was downloaded from RAAEY’s WFS service and the PVGIS yield raster from the JRC. In Python with geopandas and rasterio, I built a hexagon grid on the Greek Grid, kept the hexagons that touch land, sampled the yield on a 1 km lattice of land points in each and shared every park’s power among the hexagons by area. The printed sheet was made in ArcGIS Pro, with Kastellorizo in an inset as on Day 9; the web map draws the same hexagons with Leaflet and works out each year’s state in the browser.